What I've done
- Met with Tony Boston and Monica Berko from the National Library
(plus MLA and ALM) to discuss work they are doing in their digital
services project
and especially how they are using Blue Angel Technologies. I'll describe
this as part of the Implementation Options document (work-in-progress)
- More work on screen mockups
- Many more drafts of design document
(http://131.236.80.59/design/overview.html)
- Contacted db/Textworks vendors for information about the product
- Early drafts of Implementation Options document
- Partial update of data model documents following Hobart - more required (hope to
finish Monday)
What I haven't done but need to do soon!
- Complete update of data model based on feedback from Hobart meetings
- Talk to ALM/MLA/TW about thesaurus structure, write something up
on this for general discussion
Next week
- Meeting with NLA regarding Blue Angel.
- Finalize data model
- Discussion of design and implementation options document
- Produce an implementation plan
- Produce explicit list of issues
requiring clarification/decisions from the Partners group.
Summary
-
Next week hopefully everyone will be here (AUSTLIT side of things)
and we'll spend most of the week discussing and refining the
design documents and producing an implementation plan.